Skip to main content

Ali Lane DFWLE

This project installed 1,240 feet of 8-inch diameter treated waterline and two fire hydrants to serve eight parcels on Ali Lane in Auburn, CA.

NID's Board of Directors approved a construction contract with LaFleur Excavating.  Construction began mid-March 2024 and was completed June 3, 2024.

 

Map for Ali Lane DFWLE
Join our mailing list