Ali Lane DFWLE

This project is for the installation of 1,240 feet of 8-inch diameter treated waterline and two fire hydrants to serve eight parcels on Ali Lane in Auburn, CA.

NID's Board of Directors approved a construction contract with LaFleur Excavating.  Construction began mid-March 2024 and is expected to be completed by the end of June 2024.

As of May 8, 2024, Construction is complete.