Table Meadow Road District Financed Waterline Extension (DFWLE) Phase III
The Table Meadow Road District Financed Waterline Extension (DFWLE) is a continuation of the pipeline that was installed in Phase I and Phase II in 2017 and 2020. This is the final phase that completes the looping of the Table Meadow pipeline.
Approximately 3,260 feet of 8-inch ductile iron pipe and three fire hydrants within the Lake of the Pines Ranchos Subdivision has been installed.
The District's Board of Directors awarded the construction contract to McGuire and Hester. Construction of mainline has been tested and completed and is in service. Final asphalting is complete.